Work is now underway to prop up part of the Gateshead Highway flyover weeks after the 1960s structure was branded dangerous by investigators.
Earlier this month, engineers raised serious concerns about a concrete supporting pillar that holds up the A167, forcing the closure of the major road from December 13.
Metro services, which run underneath the bridge, were then suspended just days later over safety concerns as the crisis deepened.
North East Mayor Kim McGuinness has promised immediate action on the issue, with hopes to get Metro trains running again before finding a permanent solution to the problem.
Now, Gateshead Council leaders have confirmed work is underway to place props around a pillar that is directly over the tunnel where the Metro runs, providing additional support.
It is estimated that it will take around four days for this work to be completed.
The Metro services run underneath the flyover (Image: LDRS)
The council is working with Nexus, who operate the Metro system, on mitigating the risks so trains can run under the structure as soon as possible.
Meanwhile, replacement bus services remain in place and the flyover remains closed for all motorists, cyclists, and pedestrians.
Meetings have also been held before Christmas with the Government, the council and the North East Combined Authority, aimed at releasing funds to get demolition and the scheme for a new road underway in the new year.
Dale Owens, Gateshead Council's Chief Executive, said: "Today our contractors have started works to put propping in place, which in turn should expedite a resolution to the current transport issues.
“Our priority continues to be keeping people safe, while doing everything we can to work with our partners, particularly Nexus.
"We took the decision to close the flyover with immediate effect two weeks ago over serious safety concerns, only discovered due to our prudent close monitoring of the flyover.
“We have carried out all necessary remedial work over the years, as we worked towards plans to pull it down.
"Emergency planning has ensued ever since we closed the structure.
“This includes standing up a multi-agency tactical co-ordinating meeting through the Local Resilience Forum, with the primary focus on updating our stakeholders across the region as to achievable outcomes so contingency arrangements can be made.
"A lot of what we do behind the scenes is often largely unseen by the public, but I can assure people getting to this stage has required significant effort on our part and my thanks go to everyone who has worked around the clock to make this happen, especially given the extra pressures of this being over the Christmas period.
"We are working with our partners, key stakeholders, and the government to bring forward plans, working with the North East Combined Authority to ensure longer term relevant funding is in place.
“We agreed with the Department of Transport that this will be locally co-ordinated through a working group to be set up shortly.
"I am grateful for all the patience demonstrated by residents and stakeholders alike, who continue to follow the diversions and keep Gateshead moving and still open for business."
Recommended reading:
- Woman dies after officers called to home on Christmas Day
- Man collapsed in Darlington before he died on Christmas Eve
- Tributes pour in to ‘Mister Darlington’ Alasdair MacConachie
Get more from The Northern Echo with a digital subscription. Click here.
Meanwhile motorists are asked to follow the diversions in place with pedestrians urged to keep to the footpaths and not break through the fencing.
Security patrols are in place to ensure everyone's safety. Further council updates can be found at: www.gateshead.gov.uk/flyover
Updates on the Metro service can be found here: https://www.nexus.org.uk/metro