Search the Public Notice PortalFor almost 115 years, the Transporter Bridge has towered over Middlesbrough.
To people unfamiliar with Teesside, it might look like just a bridge. But to those living in the shadow of the structure, it is intertwined with the very identity of the region.
The Transporter symbolises the area's heritage - "steel, engineering, and graft" - and has arguably been the most recognisable icon of the area since its opening in 1911.
This month marks seven years since the Grade II* listed structure was closed due to safety concerns, which ignited fears it may never carry cars over the River Tees ever again.
The Transporter Bridge (Image: ANDY FUTERS)
Since then, engineers have been monitoring the bridge and carrying out inspections to help inform the design of a long-term solution.
The public are now waiting for Middlesbrough Council to formally put forward its proposals for the bridge, which will likely be in the form of two key options; the bridge is repaired and kept as a static landmark, or it is restored to full working order.
But there is one key issue: Funding.
Middlesbrough Council and Stockton Borough Council both share the costs of the bridge - with Middlesbrough taking the lead on managing the structure - but are unable to solely foot the bill of its repair and restoration.
Reporter Alex O'Leary interviewing Mayor Chris Cooke at The Transporter Bridge (Image: MIDDLESBROUGH COUNCIL)
Middlesbrough Mayor Chris Cooke previously said he would leave "no stone unturned" in his quest to restore the landmark - and in an exclusive interview with the Echo this week, he issues a clear message: "We will save the Transporter - and we will get the funding."
But as the wait continues for this "remarkable feat of engineering" to be returned to its former glory, the council has again come under fire for its handling of the situation.
Historian Tosh Warwick has argued that there has been a “series of catastrophic decisions and approaches” in relation to the bridge - and accused the council of having a “lack of clear vision” for its future and how it is embedded in regeneration strategies.
It comes at a time when the area surrounding the bridge, Middlehaven, continues to see major investment in the regeneration of the Old Town Hall and the construction of a new Outwood Academy Riverside just minutes away.
The Transporter Bridge (Image: ANDY FUTERS)
Many residents hold the Transporter close to their hearts and tell the Echo this week that they "do not want to see it go to rack and ruin" - but others argue funding could be a "bottomless pit" that could be used better elsewhere in the town.
Tees Valley Mayor Ben Houchen also criticised the council last year, arguing it the authority was hoping the issues would "go away" or become "somebody else's problem in the future".
However, the council has reiterated that the bridge remains a “key priority” and that it is “fully committed to its preservation and restoration”.
This week, as part of a Transporter Special Report, we take a deep dive into the bridge, the state of play, and how the next few years could unfold for the landmark of the Tees.
Saving an icon
As a structure that is more than a century old, the Transporter has long had its issues.
The bridge - which gained a reputation for regularly closing when wind speeds picked up in its later years - closed in 2019 after stretched gondola cables were uncovered.
Before that, work was carried out in 2012 when cracks were found on rail tracks on the upper booms - and there was even a near miss in 2018 when a support fell.
The year it closed, concerns it was in a "dangerous state" were raised by a whistleblower, who said wheels, ropes, and anchor points were "substantially out of date".
The council commissioned an inspection in 2020 which highlighted some areas of concerns, which were carried forward into a structural assessment in 2023/24.
It was this inspection from AtkinsRéalis engineering and consulting firm that revealed the bridge was considered to represent an immediate and unacceptable safety risk to the public.
Engineers working on the Transporter Bridge (Image: ATKINS)
It even raised fears that the bridge could be at risk of “catastrophic collapse” when wind speeds exceeded “acceptable limits”.
In the last year, the Transporter has been named on both the Heritage At Risk Register and the Victorian Society’s top ten endangered buildings list.
In April, the Victorian Society, a charity that campaigns for Victorian and Edwardian built heritage, called for a “co-ordinated national response to secure the bridge’s future”.
The Transporter Bridge (Image: ANDY FUTERS)
Since the outcome of the most recent assessment, continuous monitoring of the bridge has been in place, with more than 100 sensors tracking movement and laser scanning techniques being used to identify the bridge’s changes over time.
Work could take between three and ten years, meaning the Transporter may not welcome the public onto its working gondola until 2038, 13 years after it closed to the public.
The Transporter Bridge (Image: ANDY FUTERS)
Around £2.5m has been spent since 2019 on emergency works, surveys, assessments, repairs, lighting and the installation of digital monitoring.
Read more
Transporter Bridge named on top ten endangered buildings list
Inside the works to save the Transporter Bridge with sensors, laser tech, and drones
The truth behind the future of the Transporter Bridge six years after closure
Engineers told the Echo on a visit to the 225ft bridge last November that a “cocktail of funding” would now be needed to save it - and while the exact cost is not yet known, a report in 2024 suggested repairs could cost £67m.
This is more than double the £30m previously agreed for the bridge by the Department for Transport (DfT), an amount only accessible if the bridge is brought back into working use.
The council is now currently in the process of procuring a contractor to support the design of the restoration, and is expected to be appoint one by the end of September.
Further investigation works to support the design are likely to take place over the next three to six months, which will inform the detailed design of the works in the next year.
Interviews with the Mayor, Mr Warwick, and Middlesbrough residents, alongside a look back at the bridge's history and its future, will feature later this week as part of the Echo’s week-long special report.