Notification and Publication of an EIA Consent Decision and Regulatory Decision

Notice ID: BR3384270

Notice effective from
29th May 2018 to 28th June 2018

Public Notice -Notification and Publication of an EIA Consent Decision and Regulatory Decision
EIA Consent Decision
PD TEESPORT'S APPLICATION UNDER ARTICLE 6 OF THE TEESPORT HARBOUR REVISION ORDER 2008 FOR A TEN YEAR EXTENSION TO THE PERIOD FOR COMPLETION OF THE WORKS
The Marine Management Organisation ("MMO") has carried out an Environmental Impact Assessment ("EIA") under the Marine Works (EIA) Regulations 2007 (as amended) ("the MWRs") in relation to the extension to the period for completion of works authorised by the Teesport Harbour Revision Order 2008 ("the Order"). The works constitute a deep sea container terminal at the River Tees, Redcar and comprise capital dredging, construction of a new quay wall, reclamation and the disposal of dredged material. In accordance with Regulation 22 of the MWRs, the MMO has decided to grant EIA consent for the project on 01 May 2018.

Full details of the decision, including the environmental information taken into consideration and the main reasons and considerations on which the EIA consent decision was based can be found at: https://www.gov.uk/government/publications/teesport-harrbour-revition-order. This information may also be inspected free of charge during normal working hours at the MMO's office (a charge may be made for copies of data provided). Requests to inspect such
information should be directed to: Harbour Orders Team, Marine Management Organisation, Lancaster House, Hampshire Court, Newcastle upon Tyne NE4 7YH
Tel: 0300 123 1032
Email: harbourorders@marinemanagement.org.uk

Effect of EIA Consent Decision on the Regulatory Decision

The power to grant an extension of time has been delegated by the Secretary of State to the MMO under an agreement made under Section 14 of the Marine and Coastal Access Act 2009.
Following the above EIA consent decision in accordance with Regulation 24 of the MWRs, the MMO has decided to grant an extension of time for the completion of the works under article 6 of the Order. The regulatory decision can be found at https://www.gov.uk/government/publications/teesport-harbour-revision-order
This information may also be inspected free of charge during normal working hours at the MMO's office (a charge may be made for copies of data provided). Requests to inspect such information should be directed to:
Harbour Orders Team, Marine Management Organisation, Lancaster House, Hampshire Court, Newcastle upon Tyne
NE4 7YH
Tel: 0300 123 1032
Email: harbourorders@marinemanagement.org.uk Marine Management Organisation, Lancaster House, Hampshire Court, Newcastle upon Tyne NE4 7YH